CONAL POWER PLANT PROJECT UPDATE
MAASIM SARANGANI PROVINCE – June
11, 2015 – The Alsons Power Group’s Sarangani Energy Corporation on their
project update to local press/media Conal Power Plant project has 97%
completed.
As of 30 April 2015, a total of
2,412 personnel are at project site.
Progress and Accomplishments:
·
Boiler area (ongoing installation of steel
structure – 88% complete.
·
STG building installation of steel structure –
100% complete.
·
Main control building ongoing mechanical works –
85% complete
·
Water Treatment ongoing mechanical works – 79%
complete.
·
Workshops and Storage building Foundation and
Masonry works – 100% complete.
·
Coal crusher building mechanical works –98%
complete.
·
Coal storage building installation of steel
structure 100% complete.
·
Cooling Tower ongoing mechanical works – 43%
complete.
·
ESP Control Room ongoing installation of steel
structure 62% complete.
Watershed Protection
·
Hectares Planted Project Target 3,750 and 2,303
completed.
·
Seedlings Planted Project Target 1,875,000 and
1,012,900 complete.
·
Project Accomplishment as of April 30, 2015 –
62% complete.
Conal Power Plant project is
costing SEC U$570M investment in Maasim Municipality benefited thousands of
local residents in the area.
Power Plant expected in full
operation by the last quarter of 2015 or perhaps if project is delay will be
fully operated in the first quarter of 2016 in their projection time frame and project
Gantt Chart. According to Project Manager Fernando V. Corrales.
This Coal Power Plant will
produce 105MW power supply 70MW to supply SOCOTECO I & II, the remaining
35MW will be distributed under contract to different Cooperatives of SOCCSKSARGEN
area pass through NGCP. Corrales said.
Plant Manager JoriLumatta well
explained the details and descriptions of the Coal Plant base on his
experienced to implement projects globally. He has vast experienced to manage
Plant projects and including nuclear power plant in many countries where he
assigned.
Revenue generation from SEC of 5%
Gross Incomes in sharing scheme: 3% will go to the National government and 2%
will share to LGU of Maasim. An estimated of P10M revenue taxes shares for
Maasim Municipality a year, discussed by MaximianoAllawan one of the official
of SEC.
The historical background of
Maasim, “Quantum and conflict of area in the past, but today peace and order
has improved through the year and has benefited of 2,112 jobs for local
residents”, Vice Mayor Utto Salem Cutan said. They received P9M tax collection
from the Company, Vice Mayor Cutan exposed to the media.
The price of Coal fire plant
energy is very competitive and low to compares with bunkers power supply, PM
Corrales explained to the press.
Multi Monitoring team also has
been organized and functional since the start and commenced of the project
implementation headed and organized by DENR National and Regional office,
Corrales said.
The life span of the project base
on their Feasibility Study and Technical descriptions will be 35 years, but it
depends on the efficient and effective proper maintenance and operation. Maintenance
team of the Conal Power Plant composed of 112 personnel
to man the entire operation of the company when they fully operational at the
end of the year as projected.
Protected conveyor designed on top
of the safety standard from people and vehicles passer-bye on highway.
Contractor and company assured are out of risk in their press briefings.
Issues and concerned on
environmental protection company has already planted 40 thousands Mangroves to
protect coral reef bed from degradation. Mr. Lyndon Magtulis.
SEC Scholars’ program to poor and
deserving students with stipend allowance in the amount of P7, 800.00 and
P800.00 uniform for each student.
Local Media/press tour to plant
site as weguided and supervise by the Company Safety Engr.
By: ADLSNTV and
adlsntv.blogspot.com and Radyo ALERTO AM Station 1107Khz public affairs service
program time slot: From 3:00PM – 4:00PM every Saturday.